Kanpur: The meeting was held under the leadership of MP Akbarpur Devendra Singh Bhole and Kanpur MP Satyadev Pachauri at the Camp Commissioner Division (Kanpur) on Thursday.
The meeting was attended by members of the Airport Advisory Committee (AAC), Commissioner Division (Kanpur) DM Kanpur, Commissioner of the City, and Indian Airport Authority Officers (AAI), Uttar Pradesh Rajkiya Nigam Limited (UPRNNL), PWD and Nagar Nigam.
During the meeting was observed that the progress of the construction of new terminal buildings was unsatisfactory after officials who attended the Kanpur airport director to write a letter to MD uprnnl a warning to the blacklist of agency and impose good things if it failed to complete the previous job of the third Dedline revision from March 31 2022 .
It was told that the construction of a link and the 800 KVA underground special power supply requires permission from the New Delhi mod after the chairman and co-chairman agreed to talk to the mod.
The committee expressed their dissatisfaction with frequent cancellations from Kanpur.
So agreed upon unanimous that ILS-CAT-III must be installed.
IAF / COO told that the ILS CAT-II installation work will immediately begin and expected to be completed before 2022 October by Consultancy Under Mafi.
Further informed that the average light needs to be installed which requires the acquisition of the 600×90 square meter area.
The Chief Engineer PWD informs that the acquisition of nearly 50% of land has been completed and the construction of the road from the road to the new terminal building will be completed on March 31, 2022.