Aware of the car park bazaar ready in 2022

Aware of the car park bazaar ready in 2022
Written by news2in

Gurgaon: Two years after MCG announced the project to build multi-level car parking in aware of the bazaar to reduce the area, the Civic body only completed 20% of his work.
The project, which is estimated to cost Rs 39.93 Crore now has a new deadline because the mayor has directed engineering wing officials to complete the project on August 15, 2022.
In addition, work on other major projects from multi-level car parking.
Near the post office in conscious Bazar has not even begun.
MCG officials said that the work on the multi-level car parking project in Kaman Sarai was stopped due to encroachment by the office of political parties and unauthorized homes from MCG sanitation workers.
The work in the car park near the post office, it is estimated that the cost of Rs 49 Crore, has not yet begun because the land belongs to other government bodies and they have not transferred it to MCG, officials said.
“I have instructed the technical wing officials that development work must be resolved in a timely manner.
If a body does not start working after the work is allocated or whether the work at the speed of the snail, the action must be taken against them in accordance with the provisions To design a mechanism so that the status of this development work can be tracked online, “said Mayor Madhu Azad, who held a review of the main development project review on Tuesday.
Commissioner McG Mukesh Kumar Ahuja said in a meeting that executive engineers must regularly visit sites where the work is waiting for completion.
In addition, he said that the technical wing officials also had to visit the site before the project’s estimate was prepared.
However, some projects have begun and will be finished soon, said MCG officials.
The construction of the auditorium at Bal Bal Bhawan in Sector-4 is 90% complete, but the deadline is March 2021 but cannot be resolved due to a pandemic.
In addition, the construction of six STP along with the main pump station, it is estimated that the cost of RS 25 Crore (around) is almost complete because of 85% of the work on the project is complete.