BMC to force a 0.5% penalty on CO. For O2 plant delays – News2IN
Mumbai

BMC to force a 0.5% penalty on CO. For O2 plant delays

BMC to force a 0.5% penalty on CO. For O2 plant delays
Written by news2in

Mumbai: BMC has issued a notification that imposes a penalty in a company contracted by RS 84 Crore to install 16 oxygen generation factories in a civil hospital for failing to complete work on time.
The company, a highway construction company, who has faced bad work accusations in the past and has been punished in the BMC penguin enclosure contract, should finish factory installations in one month.
TimesViewDespite Some accusations, advanced BMC and are allowed to work to be given to polluted companies.
Now, because the company has failed to provide on time, before giving a new contract, BMC must clean up all charges and ensure that the work is given to companies that are competently transparently.
Decisive action must be taken for all delays and irregularities must be suspected.
PMC officials said that according to tender conditions, the company will face a penalty of 0.5% of the total delay.
Officials said while several sites were handed over to the company on June 16, some were submitted on June 25 and that they would count the right number of penalties for the location where oxygen plants did not operate in 30 days.
BJP has now demanded that recalling a bad company track record, BMC must demand the company from the new Oxygen Plant contract RS 320 Crore.
The last BJP was the last search of the company’s blacklist, which was awarded the RS 84 Crore contract to install the oxygen generation factory in 16 locations in Mumbai.
BJP accused the company failed to install and assign an oxygen factory in 30 days according to the work order on July 16.
“BMC must immediately make a company blacklist and file a shot into the lives of people..
Investigations must also be initiated against officials from the BMC Mechanical and Electricity Department within the contractor,” said BJP MLA Ameet Satam, who examined plants at the Cooper Juhu.
“The new RS 320 Crore contract should not be given to this company.
Instead of 1% per day, BMC imposes a penalty of only 0.5% of the total contract costs on the company,” he said.
BJP Corporator Vinod Mishra said: “We will move the Lokayukta and the Bombay High Court if the BMC provides a new Oxygen contract RS 320 Crore to the same company.
We also filed a complaint with the Wative Central Commission,” Mishra said.
P Velatu, Supplementary City Commissioner (project) said: “We have issued a notification to the company.
The sentence is 0.5% per week according to the tender conditions.
We will calculate the penalty as soon as the work ends and it will be restored.
We will take firm action against Contractors for delays and if there are irregularities.
“Romin Chedha from a highway construction company did not respond to a query.

About the author

news2in