Categories: Delhi

Delhi Metro Phase-IV deadline shaky ground

NEW DELHI: Before building work of Delhi Metro’s much-delayed Phase-IV job could gather pace following the kick-off in 2019-end, the Covid-19 outbreak caused it to a stop.
The next wave and the growing Covid situation are likely to produce the job miss its 2025 conclusion goal.
Regardless of the large challenges posed by Covid-19, Delhi Metro Rail Corporation (DMRC) continued with the building work, such as in the lockdown levied on April 19 following the exponential increase in Covid-19 instances.
There were over 4,000 employees at DMRC’s websites prior to the lockdown was enforced, but a lot of employees later chose to depart to their native regions.
“Additionally, many employees who had left before for Holi didn’t return .
This resulted in a slow reduction in the labor to approximately 2,500 individuals,” said Anuj Dayal, executive manager (corporate communications), DMRC.
Dayal stated that DMRC not simply cared for the employees who remained back with healthcare, lodging, and so on, but also attained some significant landmarks in its own Phase-IV structure job.
“Following the raising of Covid constraints, currently there’s a slow gain in the labour available,” he explained.
He explained that with progress from the Covid situation in the nation, it’s expected that building work will get additional rate, he explained, adding that numerous vaccination camps are organised in the websites to its employees and awareness campaign about the advantages of vaccination among employees continues to be conducted.
“DMRC is now engaged in building of 65 kilometres of lines around three priority corridors as part of its Phase-IV growth.
These corridors are anticipated to be finished by 2025,” he explained.
“But given the reality that the Covid situation continues to grow, the conclusion aims shall be assessed so,” he explained.
He explained that despite the many constraints triggered by the next Covid tide, DMRC continued with the building work of the Stage IV project and attained a few significant building landmarks also.
DMRC has finished tunnelling of 500 metres of among those 2.8-kilometre-long double tunnels of this Janakpuri West — RK Ashram Marg corridor.
“Delhi Metro also has finished casting of over 50 percent of tube sections at the casting yard.
The very first of these twin tunnels within this particular stretch is anticipated to be finished by September after this season,” Dayal said.
He explained that despite labour constraints, operate over the Majlis Park–Maujpur corridor, that will finish the Pink Line and also make it a’ring corridor’ is going on, such as job around the fifth bridge across the river Yamuna, that a part of the corridor and situated close to the Signature Bridge.
“Back in April and May, 2021, four important civil tenders of all DMRC Phase-IV’s underground segments were floated.
These are being financed by the loan obtained through JICA,” Dayal said.

news2in

Share
Published by
news2in

Recent Posts

44 ordered to attack the procession

Ludhiana: The police have submitted FIR to four identified and at least 40 unknown attackers…

3 years ago

Punjab: Police Reject conspiracy theory in the case of Deep Sidhu

Sonīpat / Ludhiana / Ambala: Actor Punjabi - Activist Activist Deep Sidhu, who died in…

3 years ago

Punjab: Hidden Strength Working Behind PM Narendra Modi, Arvind Kejriwal, said Rahul Gandhi

PATIALA / MANSA / BARNALA: Attacking Prime Minister Narendra Modi and AAP National Convener Kejriawal,…

3 years ago

BJP made AAP to endanger the Congress, said Ajay

Jalandhar: BJP and AAM AAM AADMI parties are one party, Secretary General of the Ajay…

3 years ago

Our job is to make Punjab No. 1 State: Meenakshi Lekhi

Ludhiana: Minister of Union Culture Meenakshi Lekhi while campaigning to support the BJP candidate from…

3 years ago

Feb 20 is an opportunity to change the destiny of Punjab and his children: Bhagwant Mann

Machhiwara (Ludhiana): AAM AAM AADMI Party (AAP) Head of Punjab Candidate and Members of Parliament…

3 years ago