ECR sets December deadlines to complete the project

Patna: After getting a budget allocation of RS 6,549 Crore, East Central Railway (ECR) has deactivated a detailed plan to complete various projects such as putting new lines, tracking multiplication and conversion gauges in various places under his jurisdiction in 20022.
-23 fiscal.
Head of Public Relations Official ECR (CPRO) Rajesh Kumar said the Union budget allocated Rs 60 Crore to put new lines between Sakri and Hasanpur.
“Also, the new line between Khagaria and Kusheshwar Astan (44km) will be placed at the end of this year with RS 60 Crore expenditure,” he said, adding a new line between Hajipur and Supaul (150km) will be placed with Rs 100 Crore expenditure.
The 92km stretch between Arariah and Supaul will be completed this year at a cost of Rs 110 Crore while the new coderma-ranchi (202km) line will be resolved on the expenditure of RS 55 Crore at the current fiscal.
Bihta-aurangabad (120km) will be resolved at the cost of RS 50 Crore this year and the new coderma-taiya line (65km) on RS 275 Crore expenditure.
Other new lines will be placed at Parasnath-Madhuban-Giridh, Fatuha-Isixampur, Neora-Daniyanwan, Daniyawan-Biharsharif, Biharsharif-Barbigha and Barbigha-Sheikhpura route.
On track doubles the segment, the train has decided to complete Ramna-Singrauli, a stretch of 160 km, on the expenditure of Rs 250 Crore in the current fiscal and a stretch of about 32 km between Karaila and Shaktinagar at a cost of Rs 160 Crore.
The road on the bridge above the Garwah road and Gomoh is likely to be ready at the end of December with RS 185 Crore expenditure.
Tracks Multiply Works at Samastipur-Darbhanga (38 km), Suguli-Valmikinagar (110km), Muzaffarpur-Suguli (101km), Darbhanga bypass (9.5km), Kiul-style (124km), Rix Dumra-Tal-Rajendra Pul Rob and Dhanbad -SheNagar (291km) route also tends to be resolved in the current fiscal, said CPRO, adding the conversion of measuring on Solid-Nirmali, Jhanjharpur-Loukha Bazar, Saharsa-Forbesganj, Mansi-Saharsa-Dauram Madhepura, Bananaagar and Jayanagar -Darbhanga -NarkatAgnaj route Complete with 1,100 crore Rs expenses.

news2in

Share
Published by
news2in

Recent Posts

44 ordered to attack the procession

Ludhiana: The police have submitted FIR to four identified and at least 40 unknown attackers…

3 years ago

Punjab: Police Reject conspiracy theory in the case of Deep Sidhu

Sonīpat / Ludhiana / Ambala: Actor Punjabi - Activist Activist Deep Sidhu, who died in…

3 years ago

Punjab: Hidden Strength Working Behind PM Narendra Modi, Arvind Kejriwal, said Rahul Gandhi

PATIALA / MANSA / BARNALA: Attacking Prime Minister Narendra Modi and AAP National Convener Kejriawal,…

3 years ago

BJP made AAP to endanger the Congress, said Ajay

Jalandhar: BJP and AAM AAM AADMI parties are one party, Secretary General of the Ajay…

3 years ago

Our job is to make Punjab No. 1 State: Meenakshi Lekhi

Ludhiana: Minister of Union Culture Meenakshi Lekhi while campaigning to support the BJP candidate from…

3 years ago

Feb 20 is an opportunity to change the destiny of Punjab and his children: Bhagwant Mann

Machhiwara (Ludhiana): AAM AAM AADMI Party (AAP) Head of Punjab Candidate and Members of Parliament…

3 years ago