Gurgaon: Two and a half years after the Gurugram Metropolitan Development Authority (GMDA) began his project to change the intersection of the city center of Huda, his work was almost complete, according to authority.
With the flyover that is ready for traffic, the intersection is likely to be open to commuter in the first half of the following month.
While it extended the project deadline from December 31, 2021, until February 10 on Tuesday, the authority emphasized that only 10% of the work on the project remained left.
“More than 90% of the work on the project has been completed.
The Flyover is ready, but the work is underway to complete the underpass and repair the service road.
Two foot-overbridges are also part of our plan, but they can be installed even after the intersection is thrown into traffic , “A senior GMDA official, who did not want to be named, the word project included Crore almost Rs 43.07 Crore.
Wild two-way 269.5 million-long between Hussain Marg and the road to the signature tower, as well as the construction of the 705m long underpass, ran from the direction of the signature tower to Subhash Chowk.
Two foot-overbridges, as well as escalators, lifts, and stairs that add it, will be installed on the road to the signature tower and other roads to IFFCO Chowk, each Pomi declares relief to be informed about the opening of the upcoming intersection.
Sumit Sinha, who lives in Sector 43, said, “The opening will facilitate the concerns of residents and commuters in this area and have long arrived.
The traffic movement at this crossroads was troubled before, but the work on the project for the past three years has also underestimated us.
ahead, we must see how effective revamp in terms of relieving traffic and pedestrian movements in the area and complications in the utility shift.
As of November last year, GMDA officials hoped to meet the December 31 deadline.
However, the prohibition of construction activities about a month above the high level of pollution in the National Capital Region (NCR) again postponed the project.
Junction City Center Huda is a critical point in the city, where traffic from Jalan Mehrauli-Gurgaon and Netaji Subhash Marg joined.
This intersection has several gated people, hospitals, offices and the last station on the Yellow Line Delhi Metro Corporation around it and see very high volumes of vehicle movements and pedestrians.