Gadkari told NMC to give up on the HNN road beauty project to the Metro – News2IN
Nagpur

Gadkari told NMC to give up on the HNN road beauty project to the Metro

Written by news2in

Nagpur: Union Minister Nitin Gadkari on Friday asked Nagpur Municipal Corporation (NMC) to submit planning, expansion, and beauty work from the road proposed in front of the train station to Mahametro.
After a review of various projects, MP City expressed disappointment too from delays in the work of the train station expansion because the existing flyover, which was intended to be destroyed.
“At present, there is no room for expansion.
And besides the elder, more space is needed for project expansion.
NMC needs to rehabilitate shop owners under the thumb in front of the Tekdi Ganesh Temple and provide it soil or money instead.
The corporation has signed a rental agreement 30 years with them.
Among them, 10 years have passed.
If the shop owner will be deleted now, they must be compensated, “Gadkari said.
The meeting was attended by Commissioner of NMC Radhakrishnan B, Mahametro’s Brajesh Dixit, Chairman of Nit Manojkumar Suryavanshi, Ravindra Thakre collector and officials from various departments.
Some officials suggest that memorandum understanding must be pressed between trains, NMC and PWD for the project.
Also occurred in the minister’s dream project from a broad metro gauge.
Officials were told that Kerala had begun working on the project.
Join also reviewing Futala Beauty Projects Plaza parking lots and a four-story building will be built along with colorful fountains.
Mahametro was asked to pay ground charges to Nit.
While discussing other projects of the Agro Convention Center in Dhaba, Gadkari directed PWD to take ownership of PDKV 14,250 SQ where he was proposed to establish a fence.
During the expansion of Jalan Keibagh, Gadkari was told that 68 residential and commercial properties, 58 had been obtained, while the rest were mired in the court process.
Gadkari asked the collector to start land acquisition by cleaning the land owner’s contribution.
Administration told him that the process would take around three months to finish it.