Gurgaon: reeling under blackouts that often occur due to damage to the DHBVN bawal substation, industrial units at BIRDI Bawal have sent SOS to the Minister of Power of State.
Industry owners complain that because of poor power infrastructure, more than 100 units are forced to operate on the generator and compromise on their production output.
According to industrial owners, they reached out Minister of Power of Ranjit Singh in June and was convinced that the new transformer would be installed in 2-3 days.
However, officials department officials have not taken any action on the guarantee given by the Minister.
President of the Gurgaon Industry Association JN Mangla told Tii, “More than 100 industries in the area are very dependent on the power supply.
Blackouts even 30 minutes annoying the entire production cycle.
This situation becomes a precarious in recent months, especially throughout June.
The only transformer Which is a supply source has become dysfunctional.
“On June 21, major damage in the transformer that serves more than 100 industries in the Bendal IMT region causes blackouts in factories.
Members of the Gurgaon Industry Association met with Minister of Power Ranjit Singh only last month and told him about the situation.
“But nothing is done so far.
I once again sent SOS requests to the minister of power and urged him to see this problem,” added Mangla.
However, Haryana Nigam Vidyut Nigam Limited (HVPNL), however, claimed that they had assigned a 100MVA transformer on June 30 and the power supply was restored on July 1.