Jammu: The Department of Development of Power Jammu and Kashmir (PDD) has decided to form a circle level audit and protection team for technical audits, maintenance and testing all 66-33 / 11-6.6KV at J & K.
The command for this effect is issued by the Development Department The main secretary’s power, Rohit Kansal today.
Commenting on exercises, the main secretary, the Department of Development, Rohit Kansal noted that the Department of Force has grappled with a number of inheritance problems related to obsolete tissue, distribution congestion and maintenance, especially preventive maintenance problems.
“This causes damage to the system that causes disruption to the distribution network and leads to discomfort for consumers.
‘He called this initiative by the Department in forming a special technical committee in a special effort to be handled sustainably and a long-term technical lack of electricity infrastructure in UT.
issued by the department asked the new protection team to be formed to test each substation of 66-33 / 11-6.6kv in the o & m circle jurisdiction at least once during the calendar year and immediately after a big mistake or the addition of new equipment / relays in Resolution.
The same order also directs the protection team to not only test and examine each substation but also conduct sub-station technical audits of all technical and safety issues such as the availability and functionality of electrical equipment in the sub-station, compliance with prevention of maintenance schedules, ketersed IAAN safety equipment and compliance with standard operating procedures (SOP) to work safely for handling blackouts and to work safely near the energy system.
Orders also asked the team to coordinate with the transmission system protection team and ensure the overall health of the electricity network.
In addition, orders also emphasize various technical steps that need to be taken to ensure that the system is protected against errors and overloaded.
Testing equipment including old stations has also been included in the scope of the protection team.
Previous chairman JPDCL, Jagmohan Sharma physically visited a number of station and recipient of the station and examined them and interacted with the field functionaries