Prayagraj: State’s initial extradosed six-lane bridge has been built over the Ganga lake from Prayagraj district.
The bridge, extending from Malak Harhar into Stanley Road (near Beli Hospital), has been assembled with the ministry of road transport and highways.
The work with this particular Rs 1,948.
25 crore project is anticipated to be finished from February 2024.
Speaking to TOI, job manager Raj Kishor Singh stated,”This could be the very first six-lane extradosed bridge from the nation.
The total length could be 9.
9 km, of which 3.
84 km will be the primary bridge and the remainder are the strategy part of this bridge” “With this particular stretch of 3.
84 kilometers, there will be 67 columns, base work of 17 columns is in procedure.
With this 3.
84 kilometers, the length of 860 meters could be extradosed bridge and the remainder will be precast segmental bridge, using a length of 50 meters.
Obviously, 860 meters, that there could be three crosses of 200 meters, so 2 of 130 meters are balancing lengths on both sides of this bridge.
Moreover, two spans 50 meters on each side of this stretch,” clarified the Indian Engineering Services (IES) officer.
He informed TOI there are a flyover of all 750 mts across the present drain involving the Stanley Road.
The bridge could begin in the Pratapgrah Road (approximately 500 meters from Malak Harhar tri-section), could get a peak to over-cross the present Y-Junction (moving towards Lucknow), could cross Ganga in Kacchar region and after crossing over Beli village, could wind up Stanley Road.
“For your commuters, wanting to proceed towards Lucknow, there are a slide road with which you will flip towards Lucknow, while people moving towards Pratapgrah or even Faizabad would remain about the bridge and land in the present Prayagraj-Pratapgrah street,” said the specialist with the abundant expertise of executing structure of Varanasi airport road street.
To accelerate the building job, a temporary street was constructed that would expedite the transportation of material and men.
The project manager stated,”We had the battle of expediting the building work in the middle of Covid-19 pandemic and lack of oxygen was just one major deterrent.
The whole price of this bridge would be 1,948.
25 crore and could be finished by February 2024.
” An extradosed bridge applies a construction which combines the key elements of a prestressed box girder bridge along with also a cable-stayed bridge.
The title stems from the term’extrados’, the upper or exterior curve of an arch, also describes the way the”stay wires” in an extradosed bridge aren’t regarded as such in the plan, but are rather treated as outside prestressing tendons deviating up in the deck.
Ludhiana: The police have submitted FIR to four identified and at least 40 unknown attackers…
Sonīpat / Ludhiana / Ambala: Actor Punjabi - Activist Activist Deep Sidhu, who died in…
PATIALA / MANSA / BARNALA: Attacking Prime Minister Narendra Modi and AAP National Convener Kejriawal,…
Jalandhar: BJP and AAM AAM AADMI parties are one party, Secretary General of the Ajay…
Ludhiana: Minister of Union Culture Meenakshi Lekhi while campaigning to support the BJP candidate from…
Machhiwara (Ludhiana): AAM AAM AADMI Party (AAP) Head of Punjab Candidate and Members of Parliament…