Finished / Alvi Times News Network Kanpur: Civil Aviation Minister, UP, NAND Gopal Gupta Nandi, visited the new Terminal Building Chakei Airport new under construction on Wednesday and expressed displeasure at a slow working rate.
He said carelessness would not be tolerated.
The government will not only submit pine against Rajkiya Nirman Nigam officials, construction agents but even send them to prison, he warns.
The agency can even be blackened in black if it fails to complete the work in the specified time, he said, and adding the construction work of the Chakei airport airport must be completed on December 31.
During the Minister’s visit to Choke 1 airport, representatives and passengers of the people had complained to him about the delay in the construction of a civil bag.
Witnessed an increase in the number of passengers at the airport and after receiving an investigation report, he learned that the construction agent was not serious in building a building in time.
Remembering complaints, the minister of flight on Wednesday visited Kanpur and led the review meeting which was attended by the regional executive director of India India Authority DK Kamra, Magistrate Kanpur Nagar, Vishak G Iyer, Rajkiiya Nigam Satyaveer officer, an additional director, the Department of Civil Aviation Wishwa Bhushan Mishra, Nodal Officer Moti Rai and Director, Chakei BK Jha Airport.
Officials told the minister that the new civil bag construction work had begun in October 2019, and only 60 percent of work can be completed in the past two years.
In this case, the Minister became angry and said that in December 2021 the construction of a new terminal must be completed in December this year.
Every carelessness will not be tolerated, he warns.
He specifically directed officials to start within 15 working days of construction of a 2.7 km-length laned approach that would connect a new terminal.
At present only one flight can be operated from Chakri Airport because it only has one apron where the plane is parked.
New civil servlave, which will have three aprons, can bear the burden of around 500 people at once and can also handle three flights at once.