Trichy Road Flyover works on a fast track

Written by news2in

Coimbatore: The national highway wing of the state highway department has completed more than 90% of trichy road tastes.
The remaining work is expected to be finished soon.
Legaran 3.15km-long will connect the stock exchange building with Rainbow Colony in Trichy Road.
To travel from Saranlatur to Ukkadam, there will be a way down along the Bypass Road.
Work on the RS 250 Crore project has begun in March 2019.
The official Department of Highways said, “The Flyover has 119 plates, which is only one remaining to be completed.
The slab that connects the main bridge with Down Ramp at Sungam Junction is waiting.
Different from the rest of the slab .
We have designed it and staging work is ongoing.
“As far as the main bridge to be considered, he said, they have completed all the work on the near side of the Stock Exchange and Bitumen ongoing ongoing.
“Near Rainbow Colony, the work to build a road approach is underway.
City Corporation moves the underground utility from the center of the road to coronary, where the path of the approach will appear.
The Civic body has placed work on the fast lane now.” Referring to the lower road, the official said encroachment must be cleaned to continue work.
He said the eviction of encroachment was postponed due to the next pandemic and locking situation.
“We can remove encroachment only after Tamil Nadu Nadu Slum Clearance Board allocates alternative accommodation to encroachment What will come in Ukkadam.
Envantation can be removed only after they move to the housing unit when it is ready, “the official said.
Layang work will be completed within three months from the date of destroying the remaining encroachment, he said.
When it is ready, the flyover is expected to reduce travel time and traffic congestion on stretches.