Categories: RanchiUncategorized

Unfinished work can delay the opening of the Sindri plant

Sindri: Even As Hindustan Urvarak and Rasayan Ltd (Hurl) Sure to start the production of commercial urea from the coming fertilizer unit in Sindri in March, the reality of land shows that it can be further extended.
The delay in the completion was bound to lead to the increase in the cost of this ambitious project from Prime Minister Narendra Modi.
After the Government NDA then decided to close all FCI loss fertilizer units (Fertilizer Corporation of India Ltd.) and HFC (Hindustan Fertilizers Corporation Ltd.) in 2002, there were no urea plants in the eastern region of the country.
Farmers must get urea from the northern and west of the country.
However, the Modi government decided to regulate the new fertilizer unit in Sindri, Baruni and Gorakhpur at a cost of Rs 6,000 Crore per unit.
Hurl, a special purpose vehicle floated by the NTPC, Cil and IOC consortium, is preparing 3,850 tons per day of Neem-based urea plants in all this place.
Modi put the foundation stone of the Sindri fertilizer unit on May 25, 2018.
The factory is expected to start commercial production in May 2021.
However, because Covid-19, the date of production may be extended until March 2022 and then March 2022.
Hurl MD AK Gupta, who recently visited Sindri to review the project, stated that the three projects were postponed 10 months due to a pandemic.
“The cost of each project has also increased by almost 1,200 crore,” he added.
GM from the Sindri project, K Jha said, “97% of the project work is complete and we are sure to be commercial production in March next year.” However, some people in saying that the construction of a plant bag building will still end because the company that built was referred to the National Law of Tribunal (NCLT) for the default on bank loans.
Hurl management has now decided to solve it through a small company contractor.
According to reports, the construction work of this building is still in the middle of the road.
Because there is no provision of silos, the production of produced must be sent directly to the bridal building and then to the platform for the next transportation via the rail, an official said.
Likewise, the rite is still in the process of putting the rail rail and scratching it.
Hurl also hasn’t completed the process of recruiting my own energy.
“If the plant will start commercial production in March, the Hall operations team must start working with the project team to get used to the factory function,” the source said.
GM, however, said that the recruitment of 98 technical people was resolved and they had begun to join the batch.
“Initially the main contractor, Technip and L & T, were to keep an eye on running the factory for 6 months and at that time our workforce would be there.
The rite must complete the channel work before March.
We strive to get the construction work of building bags that are completed on time , “he said.

news2in

Share
Published by
news2in

Recent Posts

44 ordered to attack the procession

Ludhiana: The police have submitted FIR to four identified and at least 40 unknown attackers…

3 years ago

Punjab: Police Reject conspiracy theory in the case of Deep Sidhu

Sonīpat / Ludhiana / Ambala: Actor Punjabi - Activist Activist Deep Sidhu, who died in…

3 years ago

Punjab: Hidden Strength Working Behind PM Narendra Modi, Arvind Kejriwal, said Rahul Gandhi

PATIALA / MANSA / BARNALA: Attacking Prime Minister Narendra Modi and AAP National Convener Kejriawal,…

3 years ago

BJP made AAP to endanger the Congress, said Ajay

Jalandhar: BJP and AAM AAM AADMI parties are one party, Secretary General of the Ajay…

3 years ago

Our job is to make Punjab No. 1 State: Meenakshi Lekhi

Ludhiana: Minister of Union Culture Meenakshi Lekhi while campaigning to support the BJP candidate from…

3 years ago

Feb 20 is an opportunity to change the destiny of Punjab and his children: Bhagwant Mann

Machhiwara (Ludhiana): AAM AAM AADMI Party (AAP) Head of Punjab Candidate and Members of Parliament…

3 years ago