Categories: Varanasi

Uttar Pradesh Cm Yogi Adityanath is looking for a report as 50 MLD Ramna STP in Kashi which is found overloaded

Varanasi: After skipping the parade deadline for its settlement, 50 MLD Ramna Sewage Treatment Plant (STP) has given another jolt with a net ganga mission of the United States and state government in Kashi because it has been found ‘overloaded’.
During testing capacity.
Taking a serious note about this issue, the Minister of Yogi Adyityath, on Monday night seeking a report from the Deepep Division Commissioner to improve the accountability of the Top Nigam Gang Gang Polution Unit which is responsible for preparing an estimated report of the ASI River Waste (NULLAH) and the detail of the Ramna project report STP.
CM direction came after he was told that Ramna STP’s proposal was prepared before it was launched in 2015 by estimating that the waste burden will rise to 50 mold on the Sungai ASI (Nullah), the Ganges River River.
However, when STP testing began in June, waste pressure was found more than 60 MLD.
Given CM looking for a report from the Commissioner at Ramna STP during a Monday night’s review meeting, when TII contacted Agrawal on Tuesday he admitted that STP had to be completed in March but had missed a deadline.
“When testing the STP load starts after the Basic Project work reaches the resolution threshold, waste loads found above 60 months regardless of the fact that the waste burden of up to 2030 is estimated to be 50 MLD in the DPR.
Remembering this, CM asks me to send me a report to improve accountability Officials concerned, “he told Toi.
Contacted, General Manager of the Ganga Pollution Control Unit for Jal Nigam Fanindra Rai, “During the recent meeting with the Government Authority, CM was made aware that the actual waste generator on the ASI river was around 80 MLD but had been built.
With a capacity of 50 MLD alone.
The burden of the waste burden will defeat the purpose of putting a complete waste check in Ganga.
“” Before the launch of the Ramna STP project in 2015, the estimated flow of waste in breast milk has been carried out and the DPR was prepared.
Maybe, to find about 40 mld waste flow, estimated at 50 MLD STP in Ramna will be enough to treat waste loads of up to 2030.
However, because this estimate has proven insufficient, the role of those responsible for the estimation and preparation of the DPR from the project will be examined, “Rai added.
According to Rai, a serious problem has been faced with a company that has been awarded a contract to build Ramna STP because later it was declared bankrupt it itself.
“But, the company is pressurized to complete the work assigned according to the condition of the contract at any cost,” he added, “The four complete STP basins and testing two have begun in June when testing the remaining two will begin in a week.
Some small jobs like quarters Staff, waterways and others are ongoing and they will be finished in a month.
After ruling in 2014, Prime Minister Narendra Modi has begun to ensure that his promise to examine pollution in the Ganges River is fulfilled.
Until then, against the daily generation of wastewater.
About 400 months, the city only has three STPs (80 MLD in dinapur, 10 MLD in Bhagwanpur and 10 MLD in BLW) which was made under the phase-i ganga action plan.
Modi efforts ensure the completion of a delayed job in STP – 140 MLD at Dinapur and 120 MLD STP in goithaha.
The work was completed at accelerated speed in 2019.
With its settlement, STP capacity Functional to 360 MLD.
Working on Ramna STP and 10 MLD in Ramnagar in Trans-Ganga, the transfer of OTSL in Rajghat and the Varuna corridor is being carried out to ensure the interception of all waste lines on the banks of the river.

news2in

Share
Published by
news2in

Recent Posts

44 ordered to attack the procession

Ludhiana: The police have submitted FIR to four identified and at least 40 unknown attackers…

3 years ago

Punjab: Police Reject conspiracy theory in the case of Deep Sidhu

Sonīpat / Ludhiana / Ambala: Actor Punjabi - Activist Activist Deep Sidhu, who died in…

3 years ago

Punjab: Hidden Strength Working Behind PM Narendra Modi, Arvind Kejriwal, said Rahul Gandhi

PATIALA / MANSA / BARNALA: Attacking Prime Minister Narendra Modi and AAP National Convener Kejriawal,…

3 years ago

BJP made AAP to endanger the Congress, said Ajay

Jalandhar: BJP and AAM AAM AADMI parties are one party, Secretary General of the Ajay…

3 years ago

Our job is to make Punjab No. 1 State: Meenakshi Lekhi

Ludhiana: Minister of Union Culture Meenakshi Lekhi while campaigning to support the BJP candidate from…

3 years ago

Feb 20 is an opportunity to change the destiny of Punjab and his children: Bhagwant Mann

Machhiwara (Ludhiana): AAM AAM AADMI Party (AAP) Head of Punjab Candidate and Members of Parliament…

3 years ago