Noida: With almost 40% of finished work, the signature path under construction, 697 meters of flyover in Parthala is likely to be opened to the public this July, the official authority officials on Sunday.
The RS 83-Crore project is expected to facilitate signal-free trips to more than 1.50 lakh commuters from Noida to Western Noida Greater and Ghaziabad to FNG Road in Noida.
According to authority officials, all 52 piles or foundations along with the pole lid for the project have been installed and the rest of the work is set to be completed in June.
“We will open the Flyover Parthala to the public in July this year.
For this, all jobs related to the signature bridge will be completed in June,” Mukesh Vaish, Senior Manager (Work Circle 6) from the Noida Authority, the increasing flyover said will be built Above the three pillars that have emerged about 10 meters above the ground, while the middle of the bridge will be supported by a 30 meter high pillar on both sides of the flyover, according to the design prepared by Ms.
Sri Manglam Buildcon Pvt Ltd.
So far, the authority has built pillars to a 10 meter height.
The remaining 20 meters will be completed at the end of March, officials said, adding that working on one side of the road will be completed this month.
According to officials, to keep the Parthala Roundabout unchanged, the center of the flyover is prepared as a cable suspension bridge.
“About 150 meters along the bridge will hang on 28 cables.
While the main support of the suspension bridge will be two pillars on both sides,” Vaish said.
210 meters Ramp is also being built on both sides of the bridge.
“The job on the road from the western side of Noida which will be completed in this month, while working on the road from the Noida side will be completed at the end of March,” said the official, added that the structure would be fully prepared in June while the finishing lamp and work will continue simultaneously.