Goa: 50% Mopa airport work is complete, an additional 25% on March 2022 2022 – News2IN
Goa Uncategorized

Goa: 50% Mopa airport work is complete, an additional 25% on March 2022 2022

Goa: 50% Mopa airport work is complete, an additional 25% on March 2022 2022
Written by news2in

PANAJI: Half the work at the new Greenfield International Airport in Mapa has now finished, and GMR, Goa International Airport Limited (GGIAL) has begun recruitment for the airport.
The civil aviation state director Suresh Shanbhoge told TOI that 75% of the work would be completed in March 2022, and at the same time, the Directorate General of Civil Aviation would begin testing at the airport.
During the test period, 25% of the remaining work will be completed.
“Until now, the target is inaugurated the airport on August 15 (2022),” he said.
Recently, the Ggial application invited to recruit airport rescue and fire fighters.
The total project costs have reached Rs 2.615 Crore due to delays due to the justice and pandemic process.
He said that the development center for flight skills was ready.
Work on the runway and air traffic control tower will coincide.
After the airport is assigned, “the biggest plane” will be able to land here, he said.
An official said that even after infrastructure was ready, it took around six months to secure all permits and permits needed from all authorities to start the operation.
Prime Minister Narendra Modi is likely to inaugurate the airport next year.
GMR LTD Airport, through its subsidiary, is building an airport in the Mopa highlands in Pernem Taluka.
In accordance with concession agreements, ggial will have the right to operate a business for 40 years, can be extended with another 20 years.
The airport project will be completed in four phases.
The second phase construction will begin only after 80% of passenger traffic is handled.
In 2018, the center has given the principle approval for the construction of 8 km highway from Dhargali to Varconda.
The project rate has been stopped by the court process, including a permanent order of judicial due to environmental problems.
On January 16, 2020, the Supreme Court enforced environmental permissions (EC) of the project and allowed construction to continue.

About the author

news2in