As a poll, the slow pace of the megaproject is a cause of concern for officials – News2IN
Uncategorized Varanasi

As a poll, the slow pace of the megaproject is a cause of concern for officials

Written by news2in

Varanasi: When the State Government is preparing for the inauguration of the Mega Development Project in the next two months by Prime Minister Narendra Modi in Kashi before being promulgated from the model behavior model for polls 2022, incomplete train, train, railway on the bridge (Robs ) And the streets of the Public Works Department (PWD) and UP Bridge Corporation (UPBC) have increased the concerns of officials.
Speaking with ToI on Monday, District Judge Kaushal Raj Sharma said, “Given the possibility of PM visits in the upcoming months of October and November, we are very monitoring ongoing projects.
Although many institutions and departments have been engaged to implementing projects, flying rates , Robs and road construction by UPBC and PWD have emerged as a cause of concern for us.
“The two institutions handle the Lehartara-Phulwaria-Ambitious Prison Road through the Four Shivpur Chungi Strip Project separate from other bridges, flyovers, Robs and the road to relieve congestion on the road.
DM said that the initial deadline for completing these projects was set in June and July ended.
“However, for reasons such as locking Covid-19 and the beginning of the rainy season, deadlines to complete these projects are extended and the two institutions are asked to complete the work left by the revised deadline,” he said, added, “but these agents Doing it does not increase resources including the workforce to accelerate the pace of work.
“” Thus, I will examine all of these projects on Tuesday to find out land reality and the reason why UPBC and PWD officials avoid to increase resources, “he said, added,” The relevant official will also be asked to tell about their strategy to complete the remaining work of these projects by setting deadlines.
“After PM Visit, Vanasi on July 15, when he had a talented project RS 1,593 Crores, 117 RS projects 8,871.27 Crores is underway in Varanasi.
Except for several projects, scheduled to be completed in 2022, the deadline for the resolution of the majority of projects has been determined from August to December ends by looking at the possibility of publishing notifications for assembly polls 2022 at any time after December.
DM said, “Working in the construction of the bridge in the Varuna River as part of the Lehartara-Phulwaria-Central Prison Road through the Four Chungi Chivpur Strip Project of RS 34.65 Crores is 82% complete.
Rob at the 5C Gate of Railroad Railroad Rs 62.32 Crores and Rob 4-Special Rs 88.46 Crores as part of the same project each more than 76% and 49% are ready, when the Chairman of the Minister of Yogi Adityanath has reviewed progress in September 5.
Four pathway construction by PWD with RS 166 investment , 14 crores as part of this project also 75% complete.
“The bridge in the Varuna River on Jalan Babatpur-Kapethi-Bhadohi from RS 19.14 Crores is more than 76% complete.
Rob of RS 38.10 Crore on this road is also almost 79% finished, “said the official who added,” The bridge in the Varuna River in Konia-Salarpur Road was rs 26.21 crores more than 90% complete.
“DM said that Kashi Vishwanath Dham (corridor) project work was executed by the PWD ongoing with the desired speed.
However, the official has been asked to ensure the completion of the right construction between Railway and Cantt stations from RS 18.66 crores and building construction Iti in Mahgao (Sindhora).

About the author

news2in