Ranchi: Come on Friday and Chatra, Hazaribag Regency and Koder-Long Koder Leisure will end and as well as their dependence on Damodar Valley Corporation (DVC) for the power supply to the Minister of Chief Hemant Soren will inaugurate the Chatra-Iturhori power transmission.
Lined up on that day.
“Seven countries – Bokaro, Dhanbad, Girech, Koderma, Ramgarh, Chatra and Hazariibagh – completely depend on DVC for power.
With the inauguration of the Chatra-Ikrhori transmission line, the whole district of Chatra, along with the parts of hazaribag and coderma, will no longer be must remain dependent on DVC because this area will now receive direct power from Jharkhand Bijli Vitam Nigam Ltd (JBVNL), the state-owned power distribution company, “KK Verma, who is the implementing director of Jharkhand Urja Sancharan Nigam Ltd (Jusnl), owned power transmission company The country and the Nodal Agency to put the power transmission line in the state, to TOI.
He said that the new power line would lead to the rapid industrialization of the backward area.
“Around Rs 200 Crore has been spent placing the transmission line and preparing a grid sub-station,” he added.
“This project was conceptualized for more than a decade ago, even though it was only 2019 when the Hemant government was led to take control of the control of the project taken by step.
Chatra-itkhori transmission channel passed the wooded area that was ordered where permission must be sought from the Ministry of Forestry and Delays in obtaining permits needed have created obstacles in quick implementation, “he said.
“Thermal power plants with a capacity of 1,980mW of the National Thermal Power Corporation will come on a markwalk in the Chatra District.
Phase 1 of the project with an installed capacity of 660mW is expected to be completed soon.
After this project is assigned, the new chatra-itkhori transmission channel will allow evacuation The power of the NTPC thermal power plant and allows Jharkhand to become a state of surplus power, “he added.
“The work is also active to free the dependence of Jharkhand on DVC completely.
The government of the transmission tower and laying of the transmission channel is taking place through Purulia in West Bengal to Chandankyari in the Bokaro District.
The following initiative from Soren, the West Bengal government has provided us permission to establish transmission towers.
After This project is complete, the dependence of DVC countries will be greatly reduced, “he added.
The state has purchased power at the level of Rs 4.75 per unit from DVC while cheap JBVNL power at Rs 3 per unit.
This will save a lot of savings for the state.
Apart from after 660 MW NTPC Phase 1 Text Power Power Life appears live, Jharkhand will be able to sell surplus power in Indian Energy Exchange Ltd.
or state power exchanges, with a big advantage so as to increase the flow of money, the management of JUSNL Director emphasizes.
“The DVC power line is also completely overloaded.
The newly placed JUSNL transmission line will not only ensure the supply of quality power to raise hunger districts, but will also help withdraw a number of heavy industries of steel, into it, food processing, cold storage, Air-conditioning plants etc., and improve the rapid economic development of the region dominated by the back of the country, “Verma said.