Nhai plans to complete 3 Pardi Flyover in January – News2IN
Nagpur Uncategorized

Nhai plans to complete 3 Pardi Flyover in January

Nhai plans to complete 3 Pardi Flyover in January
Written by news2in

Nagpur: After overcoming all hiccups, the National Highway Authority (NHAI) has set January 2022 as a new deadline to open the first phase of the three fifth on the important stretch of Pardi.
The overall project with five lengths of 6km will be assigned in June 2022 which benefits 55,000 units of passenger cars (PCUS).
The approved project costs are RS650 Crore, including Civil Cost RS448.28 Crore.
Work has been given to the joint venture company GDCL-SMS.
The stone for this project was placed by Prime Minister Narendra Modi on August 21, 2014.
On Friday during a site visit, Nhai showed how the project was accelerated after cleaning all obstacles, except for a patch of 86 meters near Rani Parjapati square intersection where the dispute had appeared with the owner Beer bar.
It was resolved through a high court.
Explaining the ins and outs of the unique project, regional officers Nhai Rajeev Agrawal, “The Mega project was claimed to be the first ‘open to sky’ project in Maharashtra and maybe in the country.
This project will be assigned in March 2019.” In the delay, Agrawal said, ” Some reasons.
One of them handed over 1.18-hectares of land needed for the project by NMC / NIT and the State Government, and the Drawing Approval of General Arrangements (GAD) from the Metro, which completed GADS in June 2018, and the land was handed over by various The institution in September 2020, did not include 86sqmt in Rani Prajapati Square.
“The NL Yeotkar project director said,” Civil work can only be possible after the prohibition of heavy vehicle movements for four months in the stretch.
Previously, it was done without traffic stops.
Therefore , the project cannot take full speed.
Now, the traffic transfer permit has been given.
“Agrawal said,” Also, the Seda Project NG built in a very crowded city area and there are too many underground utilities such as water pipes, electrical cables and waste phones, and waste lines.
This utility is too old and the pictures are also not available with NMC because of some difficulties encountered during construction.
“It hood the progress of the project and sometimes, the design must be changed to avoid the utility.
Finally, all utilities have shifted on May 202.
Visits to sites find that 65% of work on the project has been completed and the remaining work in the full swing.
Speaking of this project, East Nagpur Mla Krishna Khopde said, “Last year, the project had taken speed.
Of the total light length, until last year only about 0.8 km, but now 3 km long has been completed.
“Previously, for years, the 3.5km concrete road was conducted but last year, working at 7.5km was completed.
HB city intersection work has been going on in almost finished swing and foundation work and columns and superstructure works are ongoing where from 24 Girls, 16 Girders have been thrown.
“Rub work has been taken.
In addition, the foundation work at NAG River Bridge has finished and the stack closed is underway.
To this day, we have spent RS265 Crore on the project.
We plan to open the flyover from Pardi Naka to HB City to Kalamna and Itwari in January 2022, and the project balance is targeted to be completed in June 2022, “said Agrawal.

About the author

news2in