Revamp of City Center Junction is not over, wait 1 mth

Written by news2in

Gurgaon: Commuter must wait another month for Junction downtown Huda opened for them.
According to Gurugram officials Metropolitan Development Authority (GMDA), despite the two main structures – underpass and flyover – finished, some Bituminous road work and tasks such as plantations and construction of remaining pathways.
The latest deadline set for the project is February 10.
Work, GMDA officials said, delayed due to rain for the past month, as well as “winter”, because where bitumen work cannot be resolved.
At the end of March, the entire project would be completed and opened for passengers, officials said, and opposite two directions 269.5 million between Hussain Marg and the road to the signature tower.
In addition, TwoBridges two feet (FOBs) should also be arranged at the intersection – one on the road to the signature tower and the other.
The road to IFFCO Chowk.
“Over the past month, we have a number of rain splashes because there has been a delay in work.
In addition, we cannot do Bituminous work because of the winter.
Lacres and underpasses are both completed.
Only Bituminous work and several other works such as plantations and creation of paths What is left, “said a senior GMDA official.” It will take about a month for us to complete all work.
FOBS will also be installed in this period.
The work will be completed and the project will be assigned in March, “officials added.
Workers on the Crore RS 43.07 project began in July 2019, with an early 12-month deadline for its settlement.
However, construction has been repeatedly postponed by locking imposed in the midst of the Coronavirus pandemic, a shortage of workers who follow, forbid repeatedly imposed on construction due to high pollution levels, as well as complications in shifting several utilities for the project itself.
Until November last year, GMDA officials hoped to complete the project on December 31, 2021, this deadline was revised to February 10 in January after the imposition of a monthly prohibition in construction in the entire region of the National Capital (NCR).