The bad road in Bharamandala proves a curse for tourists

The bad road in Bharamandala proves a curse for tourists
Written by news2in

Madikeri: Because the construction of overbridge is delayed, tourists visit Bhagamandala, a pilgrimage site in Kodagu, affected.
The project began in 2018, but has not been completed, which affects traffic, and also causes problems for pedestrians.
Working on Overbridge in the rainy season has resulted in mud to get mud and spread throughout the city, which caused traffic congestion, and mud hunted in pedestrians when the vehicle moved on the road.
Business has been hit in stores here, because customers find it difficult to go through dirt and mud to get to shops.
The cost of Overbridge Rs 29.6 Crore, and worked on it began in 2018.
It was approved by the government to prevent traffic problems during heavy rains and floods caused by the Cauvery River overflowing.
Bharamandala BJP Office-Bearers P M Rajiv, Vinodkavedkar and others submitted a memorandum to President Panchayat Local Pamitha to clean the road by cleaning mud within a week, and threatening to launch the opposite protest.
An E Khaleem of the Irrigation Division said, “The delay in this project is caused by the issue of land acquisition and several litigation.
The acquisition process is now over.
Land surface work is finished.
Continuous rain and labor shortages due to the pandemic Covid-19 has also caused delays.
Once the rainy season arrives, it will be easier to speed up the job.