HubbalLi: Multi-level car parking work is delayed again

Written by news2in

Hubballi: Multi-level car parking construction work that can accommodate more than 300 moves at a speed of snail.
The Friday incident from compound walls collapsed because the loss of the land was the latest obstacle.
Hubballi-Dharwad Smart City Ltd.
Started the RS 50 Crore project on PPP in June 2019, to end the parking lot in Hubballi.
Since then, this project faces one problem or another.
Two locking because Covid-19 slowed the work significantly.
Now the collapse of land is not only delaying work but it has also endangered the lives of workers.
Channabasavaraj D, DGM, Hubballi-Dharwad Smart City Limited, said the multi-level car parking project was given to a company based in Hubballi based on the design-financial-finance-operate-transfer (DBFOT) in June 2019.
The work was initially postponed because it took time To get approval for design after testing the land.
The company has diged to a depth of 13.5 meters.
Around May, the land began to collapse and the company took grouting to ensure security.
Even so, this compound collapsed on Friday.
Commissioner HD Suresh Itnal said, “Because of the work at Circle Road in front of the court, Sai Mandir was closed.
DC Nitesh Patil and other officials have visited the place.
The company has been instructed to complete the retaining walls at the earliest to open the way to the public.
If the company Delaying work, strict action will begin.
“The chaos of the parking lottery project was designed to accommodate more than 300 cars in an area of ​​4,050 square meters.
But seeing work steps, this project is likely to be delayed and this will cause more traffic congestion.
When the road in front of the court is closed for traffic, congestion has increased in the KC circle, which connects to many national highways.