Bengaluru: Commercial Street, partly exhibited to the head of the BS Yediyurappa minister on Friday as another road from the city road, serves a picture of Sordid after heavy rains on Saturday: The stretch of half-a-km was exhaled with Cesspool and was damaged.
sidewalk.
Facelift, which is given by Bengaluru Smart City Limited, is the point of talks for buyers and traders with many questions, considering the fact that the crores of rupees are spent.
“The project was delayed by six months and it was relieved when CM and his colleagues visited the city shopping center and gave him a thumb.
But the road couldn’t help rain 24 hours later,” said a business owner.
The makeover project began in March 2020 and should have finished in December, but continued until last week.
Asked about the lines that moved and crossed the sidewalks that were moved, the Anand Pramod contractor said: “It has become a very boring and early project project to assess it as 50 percent of work (10 percent of civil works and 40 percent aesthetics, including lighting) still Pending.
“