Students are at risk of life every day at the unkal rly intersection

Written by news2in

Hubballi: Even when the offline class has begun for grade 6 and on it, hundreds of school students Mr.
Sakhare, Kendriya Vidyalaya No.
1 and other schools were forced to cross the railroad tracks at the Unkal train station to reach their school.
Despite the work on the railroad track under the bridge finished three months ago, it has not been opened for traffic.
Many residents in Shiradi Nagar told TOI that the construction of rubbing was completed during locking.
“Rub this aims to facilitate smooth traffic between Raj Nagar and Unkal.
Because of the absence of rubbing, we were forced to travel with Ashok Nagar.
Officials have assured that the bridge will be opened on June 202.
However, until now Inter-locked girder It has been placed to prevent vehicle movements.
When asking, authorities said they were waiting for the inauguration by selected representatives, “they said rain.
“When the offline class continued on Monday, I went to drop my daughter to school.
However, when I approached rub, what I saw was even though the work included painting was finished, there was a girder on the bridge that was still not open for traffic.
When asking, workers on the site said that their contractors had not been paid by the government, “he added.
Divedita Patil, a parent of a Sakhare School student said it was at risk of crossing the railway line at Raj Nagar Stadium.
“We are worried about children’s safety because they cross the railway line with their bikes.
The train must open the earliest rubbing for the benefit of students and the wider community,” he urged.
Hegde, Head of Public Relations, Southwest Train, said the work was taken by officials who said it was taken by Railway Vikas Nigam Limited (RVNL).
However, Indian Rail Seva, the official twitter handle of the Ministry of Railway has responded to that this problem has been intimidated to RVNL.
Will be opened within a week: Joshi “will look into this problem and ensure that rubbing will be opened for traffic.
A week,” said Pralhad Joshi, Union Minister and Dharwad MP.