Shivananda Circle Steel Flyover is ready with the end of the month – News2IN
Bangalore

Shivananda Circle Steel Flyover is ready with the end of the month

Shivananda Circle Steel Flyover is ready with the end of the month
Written by news2in

By: Pavan Kumar Pateel Bengaluru: After seeing three governments and Seemari Ministers in addition to four mayors, steel flyovers in Shivananda Circle will be ready at the end of August.
At present, 85% of work on the 493 meter flyover is over.
While all girers have been established, one plate is being thrown and the top and lower ramps are being built.
Fifteen of the 16 pillars are ready.
According to BBMP officials, 700mm water pipes that must be transferred to delayed work on the 16th pillar.
The road needs to be repaired on both sides of the flyover.
After it’s finished, it will be opened to the public gradually, officials said.
The Supreme Commissioner of the Bbmp Gaurav Gupta examined the progress of the project on Monday.
“It was delayed for several reasons.
Water pipes and sewers must be shifted, which approach three months.
Initially, the project was under litigation and then the elevated length increased.
Agreement for the revised project costs requires time.
However, the work will be completed in a month , “Gupta said to Ti.
The legisar was originally intended for a length of 326 meters.
With increasing lengths and delays, project costs jumped from Rs 19.8 Crore to Rs 39.5 Crore.
Padmavathi G congressional fighters, who were Mayor Bengaluru when the foundation stone was placed in 2017, blaming the negligence of officers for delays.
“We did get enough funds to complete the project on time.
Even though the court reselled this problem, the officers did not show interest,” he said.

About the author

news2in